TxDOT Weekly Road Work Report

befunky-design-21-png-10

Here is the latest Weekly Road Work Report from the Texas Department of Transportation Atlanta District.

This report covers January 12th through the 18th.

Bowie County

SH 8 – At Sulphur River, replacing bridges.

US 59 – At Akin Creek, replacing guard rail.

Camp County

None

Cass County

SH 8 – At Sulphur River, replacing bridges.

Harrison County

I-20 – At Potters Creek, conducting preventative maintenance work on bridges.

SH 43 – From Loop 390 to Haggerty Creek, repairing and resurfacing highway.

US 59 – From Marion County Line to Woodlawn Oaks Road, installing median barrier.

 Marion County

US 59 – From FM 2208 to Harrison County Line, installing median barrier.

Morris County

SH 49 – From Titus County Line to FM 144, repairing and resurfacing highway.

Panola County

SH 149 – At SH 315, constructing overpass and widening highway.

US 59 – at SH 149 interchange, concrete pavement replacement. East side entrance and exit ramps closed. Detours in place.

US 79 – From FM 31 to Louisiana State Line, resurfacing highway.

Titus County

SH 49 – From FM 1735 to Morris County Line, repairing and resurfacing highway.

Upshur County

None

Find out more about what’s happening at the TxDOT Atlanta District Office online.